Key facts
The City of Daytona Beach received the Florida Auditor General’s preliminary and tentative findings from their operational audit covering October 2024 through February 2026, Daytona Beach, FL said.1
The findings are not the final audit report.1
The preliminary findings identified eight issues related to building permit fee revenue, purchasing card procedures, employee travel expenses and financial oversight.1
Two areas of focus
The findings generally fall into two areas: building permit fee revenue and purchasing cards and employee travel.1
Four findings address how the city allocated and used building permit funds, including certain expenditures, vehicle purchases, employee compensation and the calculation of excess permit fee balances.1
Despite the city’s decades-long operational practice, the city has already adjusted employee payroll allocations to better align with state requirements.1
The city implemented additional financial controls for vehicles transferred between departments.1
The City Commission has also taken proactive steps to reduce excess permit fee balances, including waiving building permit fees and extending those waivers through January 2027.1
Policies updated before the audit began
In February 2026, before the audit began, the city updated its purchasing card and travel policies, strengthening procedures and clarifying employee responsibilities.1
In nearly all instances, questionable expenses identified during the review were reimbursed and additional corrective actions were taken.1
The city implemented increased internal controls during the audit process and adopted and implemented updates to outdated policies before the start of the Auditor General’s inquiry.1
What comes next
City leadership will carefully review each recommendation, address any outstanding financial adjustments and continue strengthening policies and oversight procedures.1
The city will provide a detailed, formal written response to the eight findings and additional measures planned to address each finding.1
The Auditor General will then accept the city’s response, update their audit report and issue a final audit report.1
After the final report is published, the Auditor General will schedule a public presentation to the Joint Legislative Auditing Committee sometime early next year.1